Inventory Management- Reorder. MGMT 339. Mathematics & Economics.

Coursework Instructions:

The Thompson Supply company provides a full range of products for industrial construction. Thompson buys the product from its manufacturer and then resells the product to construction companies. Its products are readily replaceable, and so a stockout typically results in a lost sales. Through its history, Thompson has maintained a reputation for having things in stock. It was often the first sourcing choice of its customers because they could rely on Thompson to have what was needed. The store is open 6 days per week.
One particular type of fastener experienced fairly steady demand of 27 units per day with a standard deviation of daily demand of 5 units. The lead time for delivery is 6 days.
a) Suppose Thompson uses a reorder point of 170 units. What is the implied cycle service level?
b)Thompson decides the reorder point of 170 is insufficient. They want to achieve a 98% cycle service level with this item. What should the reorder point be?
c) Thompson has another item that sells 1,200 units every week, with a standard deviation of weekly demand of 150 units. The lead time for this item is 3 days. To achieve a 98.5% cycle service level, what should the reorder point be?
d) A third item is ordered 26 times per year (i.e. it has 26 inventory cycles per year - it gets ordered every two weeks). It has a 97% cycle service level. What is the likelihood that Thompson will stockout of this item at least once over the course of the year?
The anwsers is a/74.22 %
b/ROP=187.11
c/ROP=830.17
d/54.7%

Coursework Sample Content Preview:

Inventory Management- Reorder
Name MGMT 339Instructor Date
The Thompson Supply company provides a full range of products for industrial construction. Thompson buys the product from its manufacturer and then resells the product to construction companies. Its products are readily replaceable, and so a stockout typically results in a lost sales. Through its history, Thompson has maintained a reputation for having things in stock. It was often the first sourcing choice of its customers because they could rely on Thompson to have what was needed. The store is open 6 days per week.One particular type of fastener experienced fairly steady demand of 27 units per day with a standard deviation of daily demand of 5 units. The lead time for delivery is 6 days.
* Suppose Thompson uses a reorder point of 170 units. What is the implied cycle service level?
* Reorder point 170 units
* Demand (D) of 27 units/ day
* Standard deviation 5 units
* Lead (L) time days 6 days
Reorder point (ROP) = Expected demand during lead time + Safety stock
Reordered point= replacement lead time * average daily usage + safety stock
Reorder point = Daily demand × Lead time + z value × standard deviation × sqrt(Lead time), 
Also,
σL= σD*L1/2= 5*6^.5= 12.25
Using the formula
Reorder point = Daily demand × Lead time + z value × standard devi...
Updated on
Get the Whole Paper!
Not exactly what you need?
Do you need a custom essay? Order right now:

πŸ‘€ Other Visitors are Viewing These APA Coursework Samples:

HIRE A WRITER FROM $11.95 / PAGE
ORDER WITH 15% DISCOUNT!