Sign In
Not register? Register Now!
Pages:
1 page/≈275 words
Sources:
No Sources
Style:
APA
Subject:
Management
Type:
Coursework
Language:
English (U.S.)
Document:
MS Word
Date:
Total cost:
$ 5.83
Topic:

Earned Value Analysis for Project Management Institute Exams

Coursework Instructions:

Earned Value Analysis for Project Management Institute Exams
This option includes practice questions similar to those found on the Project Management Institute's (PMI) certification exams. Unlike the exams, you are also asked to explain your reasoning for your choice.
If you wish to practice for the PMP exam, this option may be useful to you. If you already are certified or if you have no desire to be certified, you may still select this option. It will give you an opportunity to test your skills.
Assignment Requirements:
Use the worksheet provided for this assignment: docx
You only need to include your name, answer to the 10 questions, and provide your reasoning for each answer.
Type your answers and reasoning in a Word file for submission. There are no requirements for research or APA format.
A rubric will not be used to grade this assignment; rather, each correct answer earns five points, and each correct reason for the answer selected earns 7.5 points.

Coursework Sample Content Preview:
Module 5, Critical Thinking
Option #1: Earned Value Analysis for Project Management Institute Exams
Given a project with the following characteristics, answer the following questions:
* You are the project manager of a project to upgrade the generators at cell phone towers.
* Your project is scheduled to last for 12 months.
* It is the beginning of month 4.
* Your crews are to upgrade 8 cell phone towers per month for 12 months.
* Each generator is planned to cost $40,000 which includes equipment, labor, and fueling costs.
* You have upgraded 30 cell phone towers and your CPI is 0.96.
1 How is the project performing?
* Over budget and ahead of schedule
* Under budget and ahead of schedule
* Over budget and behind schedule
* Under budget and behind schedule
What is your reasoning? A CPI of less than 1 (0.96) indicates that the project performance is poorer than planned or over budget. 30 cell phone towers have already been completed in 3 months. The company had anticipated to complete 24 towers.
_____________________________________________________
2 Right now, what is the actual cost of the project?
* $1,800,000
* $975,000
* $1,250,000
* $2,225,000
What is your reasoning? CPI is equal to earned interest divided by the actual cost. The project’s characteristics indicate that each generator would cost $40,000. Therefore, earned value for the 30 cell phone towers equals $40,000*30, which is equal to 1,200,000. Substituting these values into the CPI equation, 0.96 = 1,200,000/actual cost
Actual cost = 1,200,000/0.96 = $1,250,000
______________________________________________________
3 Assuming that the cost variance is constant, how much more money will it take to complete the project?
* $2,500,000
* $2,750,000
* $2,800,000
* $3,000,000
What is your reasoning? Provided the cost variance remains constant, the CPI remains at 0.96. I plan to install 12*8 = 96 cell phone towers in one year. So 96 less the already installed towers (30) = 66 cell phone towers. Earned cost = 66*40,000 = $2,640,000. Actual value (money to complete the project) = Earned cost/CPI = $2,750,000
_______________________________________________________
4 What is the project’s estimated cost at completion if the variance experienced to this point stopped?
* $2,800,000
* $2,875,000
* $3,890,000
* $3,750,000
What is your reasoning? (30*41,666.67) + (66*40,000) = 1,250,000+2,640,000 = $3,890,000
________________________________________________________
5 Using the project’s budget at completion, what is the project’s TCPI?
* .5
* 1
* 1.5
* 1....
Updated on
Get the Whole Paper!
Not exactly what you need?
Do you need a custom essay? Order right now:

You Might Also Like Other Topics Related to cell phone:

HIRE A WRITER FROM $11.95 / PAGE
ORDER WITH 15% DISCOUNT!