Artisan Café Project Schedule

Coursework Instructions:

Instructions
Project Schedule
In this unit, you are required to complete the Project Schedule section of the project plan. Refer to your unit lesson (from this unit and last unit) and required unit resources to advance your project plan. For this assignment, create the components listed below.
Project Schedule: Include the duration estimates for all project activities, their activity networks, the project critical path, and estimated project duration.
4.1 Activity Duration Estimates: Include a table with activity number, activity, predecessors, optimistic duration, most likely duration, pessimistic duration, and estimated duration. Be sure to show your paths as well as the critical path.
4.2 Gantt Chart: Show the task, duration, predecessors, and the schedule leveling.
4.3 Activity Network: Be sure to include fully completed nodes, including early start, early finish, late start, late finish, and activity float/slack.
This assignment should be a minimum of two pages in length, not counting the title page and reference page. Be sure to use proper APA formatting. Citations are not required; however, if outside sources are used, make certain to provide in-text citations and references in APA format.

Coursework Sample Content Preview:

Artisan Café Project
Name
Department, Institution Affiliation
Course Code; Course Name
Instructor's Name
Date
4. Project Schedule
4.1. Activity Duration Estimates
Activity duration estimates are essential for the success of the Artisan Café market project and are described as:
Activity Number

Activity

Predecessors

Optimistic duration

Pessimistic duration

Most likely duration

EAD

1.1

Repurposing online contents

1.1

5

13

7

7.67

1.2

Monitoring online marketing progress

1.1

4

11

6

6.5

2.1

Repurposing traditional contents

1.2

8

13

10

10.17

2.2

Monitoring traditional marketing progress

2.1

3

6

4

4.17

Paths
The key paths can be correlated as 1.1-1.2 and 2.1-2.2
Critical Path
The critical path is essential for the project's success and would involve 1.1-2.1-1.2-2.2. Therefore, the critical path would be repurposing the online content by the online team. After the activity, there would be repurposing of t...
Updated on
Get the Whole Paper!
Not exactly what you need?
Do you need a custom essay? Order right now:

👀 Other Visitors are Viewing These APA Coursework Samples:

HIRE A WRITER FROM $11.95 / PAGE
ORDER WITH 15% DISCOUNT!